Total volume of CSO discharges reduced by 226.7 Million Gallons |
STONY BROOK SEWER SEPARATION (CHARLES RIVER) |
Removed stormwater runoff from neighborhood and MWRA sewers by installing 74,000 feet of new storm drains serving 609 acres in Jamaica Plain, Mission Hill and Roxbury. Completed: Sept. 2006. Cost: $45,056,000. |
Total Reduction of CSO Volume: 99.7% |
Frequency of discharges |
Before project |
22 times per year |
After project |
2 times per year |
Volume of discharges |
Before project |
44.5 million gallons/year |
After project |
0.13 million gallons/year |
SOUTH DORCHESTER BAY SEWER SEPARATION |
Removed stormwater runoff from neighborhood and MWRA sewers by installing 136,000 feet (over 25 miles) of new storm drains serving 1,750 acres of Dorchester from Dorchester Bay to Washington St. and from Columbia Rd. to as far south as the Neponset River. Completed: Dec., 2006. Cost: $118,229,000. |
Total Reduction of CSO Volume: 100%
|
Frequency of discharges |
Before project |
20 times per year |
After project |
All discharges eliminated |
Volume of discharges |
Before project |
30 million gallons/year |
After project |
All discharges eliminated |
FORT POINT CHANNEL SEWER SEPARATION |
Removed stormwater runoff from neighborhood and MWRA sewers by installing 4,550 feet of new storm drains serving 55 acres in the Fort Point Channel area. Completed: March 2007. Cost: $7,675,000. |
Total Reduction of CSO Volume: 100% |
Frequency of discharges |
Before project |
9 times per year |
After project |
0 times per year |
Volume of discharges |
Before project |
3.0 million gallons/year |
After project |
0.0 gallons/year |
PRISON POINT FACILITY OPTIMIZATION |
Minimizes treated CSO discharges to the Inner Harbor by optimizing the operation of existing facility gates and pumps to maximize in-system storage and convey more flow to Deer Island. Completed: March, 2007. Cost: $50,000. |
Total Reduction of CSO Volume: 25.4% |
Frequency of discharges |
Before project |
30 times per year |
After project |
17 times per year |
Volume of discharges |
Before project |
335 million gallons/year (treated) |
After project |
250 million gallons/year (treated) |
BOS019 CSO STORAGE CONDUIT- (LITTLE MYSTIC CHANNEL) |
Construction of new facility to provide 670,000 gallons of off-line storage in double barrel 10’x17’ conduits installed between Chelsea St. and the Mystic Tobin Bridge, Charlestown. Completed: March 2007. Cost: $14,283,000 |
Total Reduction of CSO Volume: 86.4% |
Frequency of discharges |
Before project |
13 times per year |
After project |
2 times per year |
Volume of discharges |
Before project |
4.4 million gallons/year |
After project |
0.6 million gallons/year |
UNION PARK DETENTION/TREATMENT FACILITY - (FORT POINT CHANNEL) |
Construction of new facility, adjacent to existing BWSC pump station, to provide 2.2 million gallons of storage, and treatment of remaining discharges. Completed: April, 2007. Cost: $49,546,000. |
Total Reduction of CSO Volume: 45.9%
(100% treated) |
Frequency of discharges |
Before project |
25 times per year (untreated) |
After project |
17 times per year (treated) |
Volume of discharges |
Before project |
132.0 million gallons/year (untreated) |
After project |
71.4 million gallons/year (treated) |