MWRA PIPELINE WORK TO BEGIN IN LOWER MILLS, DORCHESTER

Construction work on MWRA's Southern Spine Section 107 Phase 2 will begin in the Lower Mills section of Dorchester (Boston) on April 18, 2011.

PROJECT OVERVIEW

MWRA's Southern Spine Distribution Mains are the major water distribution pipelines for Milton, Quincy and the Southeast corner of Boston. Parts of the Southern Spine were built in the early 1900s. Some sections are very old and unlined; they have been functioning at only 50% of their original carrying capacity for years because of tuberculation (rust build-up and pocking) along the pipeline walls.

This project is being constructed in five phases, with the first three completed. It includes connections to MWRA's new Blue Hills Covered Storage Facility and the rehabilitation of more than 12 miles of water mains, valves and meters.

The Southern Spine Project will greatly increase the pipeline's delivery capacity. It will also extend its overall life span by at least 50 years and provide much-needed system redundancy for its service communities in the event of a major water main break upstream.

THIS SEGMENT

On December 16, 2009, MWRA awarded the Southern Spine 107 Phase 2 Project to RJV Construction Corp., Inc. The $14.5 million project includes the replacement of 1.7 miles of 48-inch diameter water main and the relining of an additional 4,000 feet of pipe.

Construction began in February 2010 along Adams Street in East Milton Square. The next phase of work will begin on April 18, 2011 in the Lower Mills section of Boston.

TRAFFIC IMPACTS

This work will require periodic road closures/diversions on Washington Street, Adams Street and River Street between April and November. (See construction update map for current schedule.)

If you have any questions or concerns about this project, please contact Jeffrey McLaughlin, MWRA Public Affairs (617) 660-7976.

Regular updates will be posted on mwra.com.

 

Construction Activity
in Lower Mills, Dorchester

Updated May 17, 2012

Final paving will begin on Monday, May 21, 2012. Work will cause lane restrictions and may otherwise affect traffic and parking. Please read the contractor's Paving Notice (PDF) for detailed information.

We apologize for any inconvenience and thank you in advance for your cooperation.

Planned site restoration schedule as of March 21, 2012 (PDF)

Rolling Update / Archive

Project Map project map - lower mills
Short Term Parking

(Updated April 21, 2011)

Shaws and CVS will allow short term parking for customers of Lower Mills shopping area. Shaws will allow short term parking in the below-ground garage and CVS will allow parking within the side/back lot.

Mr. Dolan from Dolans Funeral Home has also offered short term parking during times when it will not interfere with wakes or funerals.
 
The MWRA and its contractor will make up signs indicating these areas are available for short term parking during construction hours.
 
The MWRA would like to thank Shaws, CVS, and Dolans for allowing parking during these times.

Related
About the Southern Spine Distribution Mains Rehab Project
Southern Spine Section 107 Phase I (2007)
Blue Hills Covered Storage Facility
MWRA Contact
Jeffrey McLaughlin,
Public Affairs (617) 660-7976

###

Back to top

Updated May 17, 2012
Posted March 31, 2011

ß