About this Project:
This project is in design. Planned work includes the installation of 2.2 miles of 24-inch diameter water pipeline and a second MWRA meter connection to serve the City of Peabody.
For more information, please contact Jeff McLaughlin at (617) 305-5762, or by email at Jeffrey.McLaughlin@mwra.com.
09/20/2017 Update
The geotechnical program started on September 12 and will continue through October. Approximately 8 of 55 borings has been completed so far. Our contractor, CDM is finishing up the base mapping survey.